Biomass CHP plant based on an ORC cycle / STIA Holzindustrie, Admont - EU-THERMIE DEMONSTRATION PROJECT (Styria, Austria)

Relevant technical data

  • Nominal electric capacity: 400 kW
  • Nominal thermal capacities: 3.2 MW (thermal oil boiler) + 4.0 MW (pressurised hot water boiler) + 1.5 MW (flue gas condensation unit)
  • Start of operation: 1998/1999

More about the ORC-Process

Images

Fig. 1 – Click images to zoom
Fig. 2
Fig. 5
Fig. 3
Fig. 6
Fig. 4

Biomass fired CHP plant based on an ORC cycle – Project: ORC-STIA-Admont – PDF#0060

Biomasse-KWK auf Basis des ORC-Prozesses - Vorstellung der EU-Demonstrationsprojekte Holzindustrie STIA/Admont und Fernheizwerk Lienz (Österreich) – PDF#0004

Ingwald Obernberger*

*BIOS BIOENERGIESYSTEME GmbH, Inffeldgasse 21b, A-8010 Graz, Austria